Progress towards meeting environmental needs under the Basin Plan

The Department of Agriculture regularly publishes progress of environmental water recovery to improve the health of the river system under the Murray-Darling Basin Plan.

Current recoveries are as at 31 March 2019

‘Bridging the Gap’ Water Recoveries

The Murray-Darling Basin Plan sets out a local water recovery target for each SDL resource unit area along with shared water recovery targets for SDL resource units within a zone. The recovery target must be met by recovering water from within that SDL resource unit area and must be fully recovered in order to successfully ‘bridge the gap’. These include Commonwealth and state contracted water recoveries against these targets.

Surface Water Recoveries including the Sustainable Diversion Limit Adjustment Mechanism

The Sustainable Diversion Limit Adjustment Mechanism (SDLAM) amendment instrument commenced in law on the 13 January 2018.  

As set out in the Basin Plan, the SDL Adjustment Mechanism adds flexibility to the SDLs by allowing equivalent environmental outcomes of the Basin Plan to be achieved through more efficient use of environmental water (Supply Measures) and further environmental outcomes to those agreed in the Basin Plan that achieve neutral or improved socio-economic outcomes (Efficiency Measures).

The MDBA’s assessment of the package of supply measures nominated by state Governments, found that Sustainable Diversion Limits (SDL) in the southern Murray-Darling Basin can be adjusted upwards by 605 GL, reducing environmental water recovery by this amount. The Basin Plan Amendment (SDL Adjustments) Instrument 2017 which became law on 13 January 2018 allows for a full supply contribution of 605 GL LTAAY to be distributed across the southern basin. More information is available at Murray–Darling Basin Authority - Adjustment to sustainable diversion limits.

Amendments to the Basin Plan as a result of the Northern Basin Review commenced in law on 3 July 2018. The Basin plan amendment (Basin Plan Amendment Instrument (No.1) 2018) reduces the water recovery target in the northern Basin from 390 GL to 320 GL​.

Surface Water Recoveries and updated draft New South Wales factors

There are over 150 different types of water entitlement within the Murray-Darling Basin. Cap factors are an accounting tool that enable different types of entitlement to be consistently compared to track the volumes of water that has been recovered from each of the SDL resource unit. The factors are used to determine the amount of water recovery against the water recovery target in each SDL resource unit, as required under the Murray-Darling Basin Plan.

The New South Wales (NSW) Government in conjunction with the MDBA have updated the planning assumptions and calculation methods used for NSW factors. The new methods incorporate the most recent information including how much water has been recovered for the environment, historical water patterns, climatic data and trade information. Updated factors were released for public consultation and were agreed to by the MDBA for adoption in water recovery estimates on 13 February 2019. Draft cap factors are expected to be finalised when water resource plans are accredited by the Minister.  Water recovery volumes may change as plans are being finalised affecting the final volume needed to complete water recovery.

As part of the updated NSW factors work and planning assumptions, the Intersecting Streams SDL Resource Unit baseline diversion limit was re-estimated and a factor of 1.0 was determined for the entitlement of 9.72. This recovery is now included towards the Bridging the Gap recovery.

Factors for other states will be forthcoming in the coming weeks.

Summary of surface water recoveries

Two sets of water recovery tables are published with summaries below:

Water recovery data tables using v2.05 factors agreed to by Ministerial Council in November 2011
 TargetWater Recovery ProgressWater Recovery Remaining
Murray-Darling Basin
(all units in gigalitres)
Local TargetShared TargetRecovery towards Bridging the GapApportioned supply contributionLocal remaining recovery taskShared remaining recovery taskRemaining recovery task
Total Basin1668.01012.02100.5605.030.216.546.7

All water recovery figures are expressed in gigalitres long term average annual yield (GL LTAAY) terms.

Water recovery data tables using updated draft NSW factors
 TargetWater Recovery ProgressWater Recovery Remaining
Murray-Darling Basin
(all units in gigalitres)
Local TargetShared TargetRecovery towards Bridging the GapApportioned supply contributionLocal remaining recovery taskShared remaining recovery taskRemaining recovery task
Total Basin1668.01012.02082.0605.031.420.251.6

All water recovery figures are expressed in gigalitres long term average annual yield (GL LTAAY) terms.

Efficiency Contribution

Efficiency projects are water savings for the environment made through on-farm and off-farm irrigation efficiencies, as well as urban, industrial and mining.

A minimum of 62 GL of additional water savings through efficiency projects must be recovered for the full 605 GL supply contribution to be realised by 30 June 2019. Efficiency measures of 1.94 GL LTAAY have been secured or agreed in funding contracts, of which 1.28 GL LTAAY are registered with the CEWH and contribute to the required 62 GL LTAAY efficiency contribution.

The total surface water SDL for the Basin water resources as at the reference time, the time at which the Basin Plan first took effect 24 November 2012, is 10,873 GL per year. Consistent with the Basin Plan, this figure may only be adjusted through the SDLAM by a net five per cent, i.e. up or down by a net maximum of 543 GL per year. Noting that the net five per cent applies at the Basin-scale, individual SDL resources units may increase or decrease by greater than five per cent, as long as the net Basin-wide SDL remains within the five per cent range.

Murray-Darling Basin
(all units in gigalitres)
TargetRegistered water recoveryContracted water recoveryRecovery remaining
Total Basin62.01.281.9460.7

All water recovery figures are expressed in gigalitres long term average annual yield (GL LTAAY) terms.

Further information - SDL Resource Unit Shared Reduction Targets

The shared reduction amount for an SDL resource unit is determined as described in s6.05 of the Basin Plan 2012. Basin states were able to request a redistribution of shared reduction amounts could be made before 1 July 2018. Valid shared reduction requests were received from Queensland and South Australia before 1 July 2018. Further re-allocation adjustment request could be made by 31 December 2019. Valid re-allocation of shared reduction amount requests were received from New South Wales and Victoria before 31 December 2018. Shared reduction requests were formally agreed to by the Authority following agreement with the Department of Agriculture on 12 March 2019. Shared reduction targets are reflected in draft tables as at 31 March 2019.

Further details on environmental water recovery can be found below:

Efficiency measures water recoveries

The Sustainable Diversion Limit program requires efficiency measures to be progressively developed to recover an additional 450 GL consistent with the Basin Plan legal requirement to achieve neutral or improved socio-economic outcomes across the Basin by 30 June 2024.

The Australian Government is committed to efficiency measure projects to improve the efficiency of water delivery systems.

SDL Resource UnitTotal Target
GL
Total Contracted Water Recovery
GL LTAAY
Total Water Recovery registered to the CEWH
GL LTAAY
Remaining recovery
GL LTAAY
SA Murray4501.941.28448.72

All water recovery figures are expressed in gigalitres long term average annual yield (GL LTAAY) terms.

Further information

Further details on the SDL Adjustment Mechanism can be found below:

Groundwater recoveries

The Commonwealth is undertaking water recoveries that aim to protect the long-term productive base of the Queensland Upper Condamine Alluvium aquifer, consistent with the groundwater sustainable diversion limits set by the Murray–Darling Basin Plan.

Shared zone (all units in gigalitres)Local target SDL reductionShared target SDL reductionTotal recovery progressTotal recovery remaining
Upper Condamine Alluvium35.4N/A 30.74.7
Tributaries3.05N/A 0.12.95

​​All water recovery figures are expressed in gigalitres long term average annual yield (GL LTAAY) terms. Groundwater recovery does not contribute to the surface water recovery target.

Further information

A groundwater purchase tender is in the Queensland Upper Condamine Alluvium have closed and outcomes of the evaluation are now available via the department’s website.​

Further details on environmental water recovery can be found below:

​​

Last reviewed: 4 November 2019
Thanks for your feedback.
Thanks! Your feedback has been submitted.

We aren't able to respond to your individual comments or questions.
To contact us directly phone us or submit an online inquiry

Please verify that you are not a robot.

Skip